Preliminary FPC 3.0.0 release schedule
editKey Milestones
| Date | Go / No-Go | Release step |
|---|---|---|
| 2015-08-06 | 2015-08-05 20:00 CET | Tag RC1 |
| 2015-08-24 | 2015-08-20 20:00 CET | RC1 release |
| 2015-10-08 | 2015-10-07 20:00 CET | Tag RC2 |
| 2015-10-15 | 2015-10-20 20:00 CET | RC2 release |
| Tag final | ||
| Final release |
Go / No-Go
editBefore each step a meeting is held where is decided if the corresponding event can take place as planned. These "meetings" take place on irc at #fpc-dev and on the private core-mailinglist. If the decision is that a deadline can not be made, a new deadline is set.